Acceptance criteria clause examples for statements of work

Example acceptance wording for SOWs: objective criteria, a review window, deemed acceptance and a fair rejection process, with notes on when each fits.

Acceptance decides when you are finished and when you get paid. A good acceptance clause has four parts: what is tested, who tests it, how long they have, and what happens if they say nothing.

The four parts

Example: software or configuration work

Vague wording

The work is accepted when the Customer approves it.

Safer wording

Each deliverable is accepted when it passes the acceptance tests in [Appendix A]. Customer will test and accept or reject within [5] business days of delivery. A rejection must be in writing and identify the failed test; Provider will correct and resubmit for the same review. If Customer does not respond within that period, the deliverable is deemed accepted.

Example: reports, audits and documents

Vague wording

The report will be finalized to the Customer's satisfaction.

Safer wording

The report is accepted when it covers every item listed in [Appendix A]. Customer may request one round of factual corrections within [5] business days; corrections that would change the scope are handled by change order.

Example: data migration

Vague wording

Migration is complete when the data looks correct.

Safer wording

Migration is accepted when the reconciliation log shows all [number] records imported with identifiers preserved and no duplicates. Customer will review the log within [3] business days of delivery.

Common mistakes

Bracketed values are placeholders to set for your project. This is a planning aid, not legal advice.