Scope creep rarely arrives as one big request. It arrives as small, reasonable asks with no process to price them. A change clause turns "can you also…" into a decision with a price and a date.
What a change clause must say
- How changes are requested (in writing, to named contacts).
- What a change order states: the change, its effect on fees, and its effect on schedule.
- That changed work starts only after both parties sign.
- What happens to work already in progress while a change is pending.
Example: the basic clause
Risky wording
Additional requests will be discussed as needed.
Safer wording
Either party may request a change in writing. Provider will respond within [5] business days with a change order stating the change, its effect on fees and its effect on schedule. Changed work begins only after both parties sign the change order.
Example: informal approvals
Many SOWs let project leads "agree adjustments" by email or in meetings. That is fast, but it leaves fees and dates ambiguous.
Risky wording
Changes may be agreed in project meetings or by email.
Safer wording
Changes that affect scope, fees or schedule are effective only through a change order signed by both parties. Meeting notes and emails do not change the agreement.
Example: time-and-materials with a cap
Risky wording
If more effort is needed, the product owner may authorize continuation by email.
Safer wording
Work beyond the [cap amount] cap requires a signed change order that sets a revised cap and schedule before the additional work begins.
Keep it workable
- Allow small changes inside a stated tolerance (for example under [4] hours) without a change order, if both sides want speed.
- Name the people who can sign change orders on each side.
- Pause the affected work, not the whole project, while a change is decided.
Bracketed values are placeholders. This is a planning aid, not legal advice.