Workwell

SOW Check › Guides

SOW red flags: 10 clauses to fix before you sign

A practical checklist for delivery teams: the statement-of-work wording that most often turns into unpaid work, late payment or a dispute, and what to write instead.

Most delivery problems are written into the statement of work before the project starts. Read your SOW once with this list beside it. If a clause matches, fix it now, while you still have leverage.

1. Acceptance depends on "satisfaction"

"Complete when the customer is satisfied" has no finish line. Final payment can be withheld indefinitely.

Risky wording

The project is complete when the Customer is satisfied with the solution.

Safer wording

The project is complete when the deliverables meet the acceptance criteria in [Appendix A]. Customer will accept or reject each deliverable in writing within [5] business days; no response within that period counts as acceptance.

2. No deadline for acceptance

Even objective criteria fail if the customer can take forever to review. Add a review window and a rule for silence.

3. Open-ended scope words

Risky wording

Provider will provide training with unlimited revisions to materials.

Safer wording

Provider will provide training with up to [2] rounds of revisions to materials; further revisions are handled as a change request.

4. Changes "discussed as needed"

Without a written change process, extra requests become unpaid work and push the deadline.

Risky wording

Additional requests will be discussed as needed.

Safer wording

Additional requests are handled through a written change order, signed by both parties, stating the effect on fees and schedule before work begins.

5. Customer dependencies with no due date

"Customer will provide access when available" means your schedule depends on their calendar. Name what you need and when.

6. Fixed deadlines that ignore customer delays

Risky wording

The project will be completed within eight weeks of kickoff.

Safer wording

The project is scheduled for completion within eight weeks of kickoff, provided Customer meets its responsibilities on time; Customer-caused delays extend the schedule by the length of the delay.

7. Payment only on completion

On multi-week work, payment at the end means you finance the project, and every dispute blocks all of your cash. Tie payments to milestones.

8. Billing past a cap without approval

Either side being able to exceed a budget without written approval invites a dispute at invoice time. Require written approval of a revised cap before extra work starts.

9. Deliverables never actually named

If the SOW describes activities ("support", "assist", "configure") but never lists outputs, nobody can prove the work is done. List each deliverable and what "done" looks like.

10. Exclusions left unsaid

What is out of scope matters as much as what is in. One sentence of exclusions prevents months of "we assumed that was included".

How to use this list

  1. Read the SOW once, start to finish, before marking anything.
  2. Mark every clause that matches an item above.
  3. For each one, check whether another clause already fixes it (a change-order section can cover item 4).
  4. Propose replacement wording rather than just flagging the problem; specific edits get accepted faster.

This is a planning aid, not legal advice. For high-value or unusual agreements, have counsel review the final text.

Check your own SOW against this list

Upload the Word file and get it back in a couple of minutes, with every fix marked.

Choose your SOW